Good morning, Boss Justine Roi D. Golez ☀️
Your 6AM briefing ·
You have 4 active projects running today. SBE Building is the priority — currently at
78% actual vs 98% scheduled (20 points behind).
Critical blocks: Roof Installation hasn't started (9.5% of total work), Sag Rod at 0%,
Flooring Pouring stuck at 30%, and all 4 Cladding activities are not started.
Heads up: Labor Admin is ₱240K over budget. Pakyawan margin is healthy at 41%.
Recommended action today: Reassign 6 welders from completed H-Beam work to Sag Rod + Roof Install to recover 5-8% this week.
Recommended action today: Reassign 6 welders from completed H-Beam work to Sag Rod + Roof Install to recover 5-8% this week.
Active Projects
4
1 critical · 3 on track
Schedule Variance
-20pts
▼ Behind schedule
Contract Margin
41%
▲ ₱177K Pakyawan margin
Labor Admin
₱240K over
▼ 40% above budget
Team on Duty
28/32
2 late · 2 absent
🏗️ SBE Building — Private Client Oil Mill
Quotation #2025-039 · PO #51425407 · ₱3,154,889.18
Overall Progress
78% actual · 98% scheduled
Started: Jan 10, 2026
Target: May 18, 2026 · Day 104 of 128
Spent
₱1,585,253
50% of contract
Remaining Budget
₱943,949
+ ₱582K contingency
🚨 Critical Activities Blocking You
A.20
Roof Installation
0%/ 70% sched
A.18
Sag Rod
0%/ 100% sched
A.11
Flooring Pouring
30%/ 100% sched
A.22-27
Cladding (East, West, North, Gutter) · 6 activities
0%/ 30% sched
🏭 Other Private Client Projects
569
Drag Conveyor Casing Installation
VCR
Vertical Cooker Rescue
FR
Flaker Rescue
⚡ Quick Actions
👥 Team Today
28 of 32 on duty · From biometrics
✅ On duty
28
⏰ Late (after 7:15 AM)
2
❌ Absent / No scan
2
🦺 Safety permits today
3