📊 Bar Chart & Gantt — SBE Building

27 activities · Day 104 of 128 · Recovery plan needed
20% behind
A.12 Fabricate Trusses
100%
A.7 Column Pouring
100%
A.10 Laying CHB
100%
A.9 H. Beam
100%
A.14 Install Trusses
100%
A.17 Cee Purlins Install
90%
A.19 Cross Bracing
60%
A.11 Flooring Pouring
30%
A.18 Sag Rod
0%
A.20 Roof Installation
0%
A.22-27 Cladding (6)
0%
💡 JAKIS insight: You have 5 activities with 0-30% progress but original schedule says 70-100%. Suggest reallocating 6 welders from completed H-Beam to Roof Install + Sag Rod starting Monday to recover ~7% variance this week.

📦 Materials Used — Latest Withdrawals

View Full Ledger
Date Material Qty Activity Cost
Apr 24Cement 40kg15 bagsA.11 Flooring₱3,225
Apr 24DRB 12mm x 20'8 LGTA.14 Trusses₱1,712
Apr 23Cotton Gloves2 dozGeneral PPE₱360
Apr 23Welding Rod 601110 klsA.19 Cross Bracing₱2,000
Apr 22Sand (4 cubic)1 truckA.11 Flooring₱1,500

📋 Site Inspections

+ New
Column alignment checkPassed
Apr 24, 8:30 AM · By Supervisor 1
Rebar spacing verificationPassed
Apr 24, 7:15 AM · By Supervisor 2
Truss welding qualityRe-do needed
Apr 23, 4:20 PM · By Supervisor 3

👥 Employees Today

Welders on site 14/15
Laborers on site 5/5
Running overtime 3
Last synced 7:32 AM biometrics
🧠